• Hut 8’s bitcoin mining operation in North Bay, Ontario has come to a standstill after a disagreement with its Canadian-based energy provider, Validus Power.
• Validus has stopped supplying power to the facility while delivering its own default notice for payments that it claimed Hut 8 failed to make and has demanded that the company make payments for delivery of energy higher than those negotiated.
• Hut 8 is continuing to explore alternatives to mitigate the impact of the dispute, including through organic and inorganic growth opportunities.

Hut 8’s bitcoin mining operation in North Bay, Ontario has come to an abrupt standstill due to a disagreement with the Canadian-based energy provider, Validus Power. A notice of default was issued by Hut 8 to Validus in November 2022 for failing to hit certain operational milestones. This was followed by a complete halt in mining operations two weeks later, as Validus stopped supplying power to the facility and issued their own default notice for payments that they claimed Hut 8 had failed to make. Furthermore, Validus demanded that Hut 8 make payments for delivery of energy higher than those originally negotiated under the terms of the purchasing agreement.

Uncertainty in power costs can have a significant influence on bitcoin mining operations, making favorable power purchasing arrangements essential for a sustainable firm. In response to the dispute, Hut 8 has been actively seeking alternatives to mitigate the impact of the situation, including through organic and inorganic growth opportunities. In their most recent December update, the company expressed their full intention to resolve the issues and to restart operations as soon as possible, either through a resolution involving Validus, or by finding a potential alternative power supplier.

As Hut 8 continues to explore different options, the resolution of the dispute with Validus remains a key factor in the success of their operations. With the company’s commitment to resolve the issues and their proactive approach to mitigate the impact of the dispute, the resolution of this disagreement is expected to be a major milestone for the firm.